ZRP
Tuca Zbarcea & Asociatii

Developing Renewables in Romania: PUZ or Pass?

17 Octombrie 2022   |   Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & Partners

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.

 
 

One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.

To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.

1.          Types of lands

The following lands qualifications are relevant for the current topic:

(i)         from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);

(ii)       from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;

(iii)      from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.

2.          General construction rule

As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.

If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),

(i)         the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;

(ii)       no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.

3.          Exception dedicated to renewable energy projects

Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:

(i)         land has fertility class III, IV and V; and

(ii)       land does not exceed 50 ha.

Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.

4.          Need of a PUZ in case of renewable projects below 50 ha

Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?

The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.

Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:

(i)            according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;

(ii)          all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);

(iii)        PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;

(iv)        if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;

(v)          generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;

(vi)        very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.

Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 1041 / 4679
 

Ascunde Reclama
BREAKING NEWS
ESENTIAL
LegiTeam: GNP Guia Naghi and Partners is recruiting new talent | Dispute Resolution and Arbitration
CMS a fost alături de Oresa în vânzarea participației deținute la RBC, cu o echipă condusă de partenerii Horea Popescu și Eva Talmacsi (UK). O echipă coordonată de Ana Radnev (Partner) a asistat și creditorii în finanțarea sindicalizată asociată tranzacției
LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocat stagiar | Litigii
Băncilă, Diaconu și Asociații își consolidează practica de achiziții publice printr-o creștere robustă a mandatelor strategice, o orientare fermă către sectorul apărării și securității naționale și o metodologie integrată care acoperă întregul ciclu al procedurilor, de la pregătirea documentației până la implementarea contractelor | De vorbă cu Andrei Ștefanovici și Andra Iftemie despre transformările prin care trece întreaga piață a achizițiilor publice
Cum arată, din interior, practica de insolvență a unei firme poziționată în Tier 1 de directoarele internaționale. “Clienții au așteptarea să reușim imposibilul în ultimul moment posibil”, spun Emil Bivolaru și Florentin Nanu, NNDKP, într-o discuție despre primele 72 de ore care definesc un dosar, sofisticarea mandatelor cu expuneri fiscale și motivele pentru care cadrul legislativ al reorganizării trebuie reformat structural
RTPR, alături de US EXIM în finanțarea acordată EnergoNuclear. Partenerii Victor Pădurari și Cosmin Tilea au coordonat echipa
Advent finalizează achiziția TBI Bank în Bulgaria și România. Kinstellar, alături de Milbank LLP în calitate de lead counsel, a asistat pe tot parcursul tranzacției cu o echipă coordonată de Zsuzsa Csiki (Partener) și Mihai Stan (Managing Associate)
LegiTeam: Reff & Associates is looking for a 3 - 6 years Attorney at Law | Dispute Resolution
EXCLUSIV : Judecătorii CJUE au audiat cel mai important caz de concurență venit din România până acum - Cauza C-357 ̸ 25 Groupama Asigurări. Valentin Berea (Partener RTPR) a coordonat apărarea asigurătorului român în acest caz, cu o echipă mixtă RTPR ̸ A&O Shearman, din care au făcut parte avocați din România și Ungaria | Valentin Berea, pentru BizLawyer: „Este genul de caz care te face să îți iubești profesia”
DLA Piper pierde un partener | Livia Zamfiropol pleacă la Dentons pentru a conduce practica de concurență și activitatea biroului în sectorul Pharma & Healthcare
Ghid pentru clienții sofisticați | Cine domină arbitrajul comercial din România: avocații și firmele recunoscute de Chambers, Legal 500, GAR 100 și Lexology. Dr. Cosmin Vasile se detașează ca „the leading star” pe piața locală, fiind descris de ghidurile internaționale drept cel mai complet avocat de Dispute Resolution din România. ZRVP, TZA, NNDKP, Filip & Company și PNSA au cele mai solide practici locale de arbitraj și ar trebui să fie primele alegeri ale firmelor care caută sprijin în dispute guvernamentale și corporative
Ghid pentru clienții sofisticați | Cum arată, în 2026, ierarhia firmelor internaționale de avocatură din România, creionată de Chambers Europe și Legal 500: CMS se detașează ca lider prin amploarea și diversitatea platformei sale, iar Clifford Chance își conservă profilul de firmă de referință în domeniul finanțărilor. Mai jos în clasament, dar pe podium, DLA Piper Dinu și Dentons își confirmă forța în câteva arii de practică, iar Eversheds are o prezență modestă
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...