No More PUZ for Developing Renewables
10 Ianuarie 2023 Mihaela Nyerges (Partner) and Diana Dulama (Junior Associate) - Nyerges & Partners
This amendment is a huge breakthrough, as it may reduce the duration of the development process with up to 9 months.
| |
Very good start of the year for the renewable energy sector.The much-awaited legislative intervention was passed: PUZ is no longer required for developing renewable energy projects.
When Land Law no. 18/1991 was changed last summer to allow the development of renewable energy projects on extra muros lands (to the extent such lands do not exceed 50 ha per investment project and have III, IV or V fertility class), the entire industry expected that the zonal urban plan (PUZ) would no longer be required for such projects. PUZ is one of the most time-consuming stages of the permitting process. However, despite the non-unified practice of the local authorities, the general interpretation was that PUZ was still mandatory.
Such interpretation was based on the fact that, although not expressly required by the Land Law, PUZ continued to be a requirement for the issuance of the building permit according to the general construction and urbanism legislation.
When Land Law no. 18/1991 was changed last summer to allow the development of renewable energy projects on extra muros lands (to the extent such lands do not exceed 50 ha per investment project and have III, IV or V fertility class), the entire industry expected that the zonal urban plan (PUZ) would no longer be required for such projects. PUZ is one of the most time-consuming stages of the permitting process. However, despite the non-unified practice of the local authorities, the general interpretation was that PUZ was still mandatory.
Such interpretation was based on the fact that, although not expressly required by the Land Law, PUZ continued to be a requirement for the issuance of the building permit according to the general construction and urbanism legislation.
However, further to a new law that was just promulgated by the Romanian President (yet to be published with the Official Gazette), the Constructions Law no. 50/1991 was amended in the sense that no urbanism documentations are necessary for renewable projects fulfilling the above limitations related to land size and fertility class. Therefore, for such projects, the only permitting requirements are, essentially: (i) obtaining the decision for removal of the land from agricultural circuit (from the competent local agricultural department, based on the prior endorsement of the Ministry of Agriculture and Rural Development) and (ii) the building permit.
This amendment is a huge breakthrough, as it may reduce the duration of the development process with up to 9 months.
Unfortunately, through such intervention, the legislator did not amend also other provisions of the Constructions Law no. 51/1990 and Urbanism Law no. 350/2001 which impose the amendment of the existing urbanism documentation whenever the envisaged project does not comply with the specifications thereof. We can only hope that this will not trigger contradictory interpretations in practice and that it will be remedied shortly by the legislator. Also, the approach of the local authorities as regards the urbanism certificates that were already issued (and whereby PUZ was requested for the building permit) is yet to be seen.
It remains unsolved the permitting of renewables projects on lands exceeding 50 ha or having fertility class I and II. For these projects, PUZ continues to be mandatory (both for requalifying the land as intra muros and for establishing compatible urbanism parameters/function) and the process is still blocked at the level of the Ministry of Agriculture and Rural Development, which refuses to issue its mandatory PUZ endorsement.
Nyerges & Partners is a boutique law firm offering a full range of legal services. Our expertise in the energy field spans over 15 years, our team having assisted the most important players on the Romanian market (producers, grid operators, suppliers, developers). As regards the renewable energy, our team has an impressive portfolio of completed and ongoing projects, and extensive experience in all stages of such projects: acquisition, development, construction, operation and financing.
| Publicitate pe BizLawyer? |
![]() ![]() |
| Articol 823 / 4601 | Următorul articol |
| Publicitate pe BizLawyer? |
![]() |
BREAKING NEWS
ESENTIAL
Patru firme de avocați, în proiectul prin care Banca Transilvania a finalizat cu succes cea mai mare emisiune de obligaţiuni AT 1 din Europa Centrală şi de Est
Kinstellar a asistat Lidl în achiziția unui teren situat în incinta fostei platforme industriale Aversa din București. Victor Constantinescu (Partner) și Sandra Gheorghe (Senior Associate), în prim plan
GNP obține o nouă soluție favorabilă definitivă la Înalta Curte de Casație și Justiție prin care a fost anulată o decizie de sancționare emisă de Consiliul Concurenței | Reper jurisprudențial care impune un standard de analiză mai riguros în litigiile de concurență
PNSA asistă Rex Concepts în obținerea unor linii de finanțare de la Bank Pekao pentru dezvoltarea rețelelor Burger King și Popeyes | Echipa de proiect a fost coordonată de partenerul Silviu Stoica, alături de Ioana Lazăr (Senior Associate) și Crina Stan (Associate)
Băncilă, Diaconu și Asociații a asistat asociații Mamaia Resort Hotels în vânzarea părților lor sociale către Steaua de Mare Hotels & Resorts
Fiscalitate ̸ Litigii Fiscale - Practica de Taxe a Kinstellar funcționează ca un „hub” integrat între drept, fiscalitate și finanțe, ce conturează un parcurs procedural previzibil, din faza de control al documentelor până la soluțiile finale ale instanței. Clienții beneficiază de pregătire proactivă, probatoriu robust și o echipă calibrată pentru litigii sofisticate | De vorbă cu Theodor Artenie (Counsel) și Raluca Botea (Counsel) despre tendințele ultimului an, prevenție, timing și modul de lucru al unei echipe recunoscute de directoarele internaționale
Schoenherr asistă Allianz-Țiriac Asigurări în vânzarea unei clădiri de birouri către Primavera Development. Echipa, coordonată de Mădălina Mitan (partner)
Clifford Chance Badea a asistat Aukera Energy în obținerea unei finanțări de 60 mil. € pentru primul său proiect de stocare a energiei pe bază de baterii din România
LegiTeam: GNP Guia Naghi and Partners — Corporate | M&A Associate (2–4 years)
Primul pas real spre avocatura de business | În culisele programului de practică juridică organizat de Țuca Zbârcea & Asociații, o adevărată școală de formare și începutul unui dialog profesional. Cursanții implicați în program au apreciat comunicarea continuă și proiectele în care au fost implicați și ar recomanda această experiență altor studenți. Avocații-mentori spun că experiența de practică autentică oferă prilejul de a înțelege care sunt valorile ce definesc profesia
Clifford Chance Badea a asistat consorțiul de bănci de investiții în legătură cu emisiunea de obligațiuni de 600 milioane Euro lansată de DIGI România
Cum arată, din interior, practica de Concurență de la 360Competition într-un an cu FDI intens, investigații tot mai tehnice și o presiune procedurală care schimbă regulile jocului | De vorba cu Adrian Șter (Managing Partner) despre axele de lucru care definesc practica, evaluarea corectă a riscului şi „linia de apărare” oferită clienţilor. Modelul senior-led bazat pe echipe compacte, rapiditate în decizii şi claritate în recomandări, arată de ce un boutique specializat e chemat frecvent acolo unde mandatele devin prea complicate pentru abordări standard
Citeste pe SeeNews Digital Network
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...









RSS