Nuclearelectrica seeking agreement with Romanian state on financing, support for construction of Cernavoda NPP Units 3 & 4
08 Martie 2021 Agerpres
The company also specifies that the project's feasibility study is ready, but can be consulted only by the shareholders, at the company's headquarters, under the condition that they sign a confidentiality agreement.
Cernavoda nuclear power plant operator Nuclearelectrica (SNN) will make the decision to invest in the construction of NPP Units 3 and 4 provided that it concludes an agreement with the Romanian state establishing the financing method and support mechanisms for this project, states the 'Strategy for the continuation of the Units 3 and 4 project", a document that will be discussed in the General Meeting of the Company's Shareholders scheduled for April 5, 2021.
The document sets forth the following: "As a precondition for taking the preliminary investment decision and moving to the 2nd stage of the project, it is necessary for SNN to conclude an agreement with the Romanian state, establishing the responsibilities of the parties regarding the provision of financing, the adoption of support mechanisms and the provision of infrastructure requirements for the completion and operation of the project."
The company also specifies that the project's feasibility study is ready, but can be consulted only by the shareholders, at the company's headquarters, under the condition that they sign a confidentiality agreement.
"In December 2020, the Deloitte and Kinectrics association finalized the update of the 'Feasibility study for the completion of the project of Cernavoda Units 3 and 4' (Annex 1 - Updated Feasibility Study ); the conclusion of the feasibility study was that the project of Units 3 and 4 is financially sustainable and the cash flow requirements are met," say the SNN representatives.
Regarding the implementation of the Cernavoda Units 3 and 4 project, international practices show that the allocation of high risk capital is necessary in the preparatory/pre-project phase, in order to properly define a nuclear power project in a way that allows the final investment decision to be made.
In order to restart the project, and taking into account the best international practices in the field, the strategy proposes a step-by-step approach for implementation, ie dividing the project into three distinct development stages.
The first is the preparatory stage, the Preliminary Notice to Proceed (Pre-LNTP), with an estimated duration of 24 months and an estimated budget of 15 million euros that will be financed by SNN, by increasing the share capital of Energonuclear (EN) - the company tasked with the construction, commissioning and operation of Units 3 & 4 - accordingly. The main objectives of this stage are: re-operationalization of project company EN, contracting technical, legal and financial assistance services, contracting engineering services to update the technical procurement specification, launching, selecting and awarding the Engineering, Procurement and Construction Contract in two phases (Phase 1 - Preliminary Works - Limited Notice to Proceed and Phase 2 - Project Implementation - Issuance of the Final Notice to Proceed).
Any other studies/reports/evaluations necessary for the configuration of the project within the limits of the budget assigned to this stage shall be contracted within this stage.
The second stage consists of the preliminary works (Limited Notice to Proceed - LNTP) - Phase 1 of the Engineering, Procurement and Construction (EPC) Contract, with an estimated duration of 18 - 24 months. The objectives of this stage consist in the development, by the EPC contractor, of the critical engineering part of the project, of the nuclear safety documentation and of the local market surveys in order to identify the necessary equipment and service suppliers, so that the total price of the project is fixed for a considerable part of the necessary works and services.
The nuclear safety documentation required for obtaining the Nuclear Safety Authorization will also be developed in this stage, as well as the documentation for the project's notification to the European Commission, based on Article 41 of the EURATOM Treaty.
At the end of this stage, the feasibility of the project will be re-assessed based on the new technical and economic indicators and the Final Investment Decision will be taken, which will allow moving to project Stage 3.
A set of requirements must be met for the Final Investment Decision to be taken, including obtaining the necessary authorizations from the European Commission for the support measures and structuring and closing the project's financing package.
The third stage is represented by the effective construction stage (Issuance of the Final Notice to Proceed - FNTP) - Phase 2 of the EPC Contract, with an estimated duration of 69 - 78 months (completion of Unit 3 - 2030 / completion of Unit 4 - 2031), consisting in the effective start of the construction, assembly and commissioning works.
One week ago, SNN general manager Cosmin Ghita said that he expects the construction of the new reactors to start in 2024.
"We anticipate Unit 3 to be commissioned around 2030 - 2031, according to the Integrated National Energy and Climate Change Plan, which means a mobilization on site around 2024. Preliminary phases are scheduled until then," said Ghita.
| Publicitate pe BizLawyer? |
![]() ![]() |
| Articol 3344 / 4686 | Următorul articol |
| Publicitate pe BizLawyer? |
![]() |
BREAKING NEWS
ESENTIAL
Filip & Company a asistat Christian Tour în cadrul ofertei publice inițiale și al listării la Bursa de Valori București | Echipa a fost coordonată de Olga Niță (partener)
Urmează o perioadă de tranziție critică pentru piața achizițiilor publice din România, marcată de presiuni simultane din direcții multiple. Creșterea cheltuielilor de apărare va genera un volum semnificativ de proceduri complexe, cu specificități juridice pe care puțini practicieni le stăpânesc în detaliu | De vorbă cu Manuela Guia, coordonatoarea GNP Guia Naghi & Partners, despre noile zone de sofisticare juridică și câteva măsuri prin care ar putea crește transparența și viteza procedurilor fără a afecta calitatea evaluării
RTPR asistă EMSA Capital în tranzacția de exit din Aplast
Employment Roundtable Filip & Company: Piața muncii intră într-o zonă de tensiune: restructurările și investigațiile interne devin noua realitate pentru companii
Schoenherr și Legal Ground, în linia întâi a unei tranzacții cu mai multe clase de active prin care Piraeus își restrânge expunerea reziduală din România | Un portofoliu cu credite, leasinguri, participații de risc, garanții și active imobiliare a pus avocații în fața unui mandat aflat la intersecția dintre M&A, banking & finance și real estate
Mușat & Asociații obține o decizie de referință pentru salariații Hidroconstrucția, societate în reorganizare judiciară, cu impact estimat de 1,2 mil. € | Echipa, coordonată de Mihai Popa (Deputy Managing Partner)
NNDKP a asistat Raiffeisen Bank România în legătură cu finanțarea grupului Monza Ares în vederea achiziției Brain Institute și integrării acestuia în structura grupului | Alina Radu (Partener) și Cătălina Dan (Asociat Senior), în prim plan
Mitel & Asociații a asistat vanzatorii în tranzacția prin care Grupul Monza Ares, susținut de Highlander Partners, a preluat centrul privat de neurochirurgie Brain Institute | Mădălina Mitel, coordonatoarea echipei de proiect: ”Pentru noi, un mandat de M&A reușit este acela în care soluția juridică susține logica economică a tranzacției și permite părților să meargă mai departe cu un proiect viabil”
NNDKP a asistat grupul PPC în procesul de negociere pentru încheierea noilor contracte colective de muncă | Roxana Abrașu (Partener) și Daniel Stăncescu (Managing Associate), în prim plan
RTPR asistă Silcotub la achiziția Artrom Steel Tubes. Echipa, coordonată de Mihai Ristici (Partener) și Vlad Stamatescu (Counsel)
Florian Nițu (PNSA), singurul avocat din România aflat în cursa pentru titlul „CEE Partner of the Year” la ”Legal 500 Central and Eastern Europe Awards 2026” - nu doar într-un an mai bun, ci după două decenii de consecvență în excelență: „Avocatul a devenit, în fapt, un ‘integrator’ în proiectele complexe, responsabil de alinierea componentelor juridice, comerciale și operaționale ale unei tranzacții. Clientul este azi un partener strategic, sofisticat și continuu implicat în gestionarea serviciului avocațial”
Mandatele sofisticate, în care soluțiile juridice trebuie dublate de înțelegerea mecanismelor economice, confirmă forța practicii de Insolvență & Restructurare a ZRVP, evidențiată în Tier 1 de Legal 500 | Alexandru Iorgulescu (Partener): ”Pot spune că specific practicii noastre sunt mandatele complexe ce reclamă soluții inovatoare, unde lucrăm adesea pe drumuri ‘neumblate’ și în care problemele de dreptul insolvenței se întrepătrund cu cele civile, societare, administrativ-fiscale”
Citeste pe SeeNews Digital Network
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...









RSS