ZRP
Tuca Zbarcea & Asociatii

Nuclearelectrica seeking agreement with Romanian state on financing, support for construction of Cernavoda NPP Units 3 & 4

08 Martie 2021   |   Agerpres

The company also specifies that the project's feasibility study is ready, but can be consulted only by the shareholders, at the company's headquarters, under the condition that they sign a confidentiality agreement.

 
 
Cernavoda nuclear power plant operator Nuclearelectrica (SNN) will make the decision to invest in the construction of NPP Units 3 and 4 provided that it concludes an agreement with the Romanian state establishing the financing method and support mechanisms for this project, states the 'Strategy for the continuation of the Units 3 and 4 project", a document that will be discussed in the General Meeting of the Company's Shareholders scheduled for April 5, 2021.
 
The document sets forth the following: "As a precondition for taking the preliminary investment decision and moving to the 2nd stage of the project, it is necessary for SNN to conclude an agreement with the Romanian state, establishing the responsibilities of the parties regarding the provision of financing, the adoption of support mechanisms and the provision of infrastructure requirements for the completion and operation of the project."
 
The company also specifies that the project's feasibility study is ready, but can be consulted only by the shareholders, at the company's headquarters, under the condition that they sign a confidentiality agreement.
 
"In December 2020, the Deloitte and Kinectrics association finalized the update of the 'Feasibility study for the completion of the project of Cernavoda Units 3 and 4' (Annex 1 - Updated Feasibility Study ); the conclusion of the feasibility study was that the project of Units 3 and 4 is financially sustainable and the cash flow requirements are met," say the SNN representatives.
 
Regarding the implementation of the Cernavoda Units 3 and 4 project, international practices show that the allocation of high risk capital is necessary in the preparatory/pre-project phase, in order to properly define a nuclear power project in a way that allows the final investment decision to be made.
 
In order to restart the project, and taking into account the best international practices in the field, the strategy proposes a step-by-step approach for implementation, ie dividing the project into three distinct development stages.
 
The first is the preparatory stage, the Preliminary Notice to Proceed (Pre-LNTP), with an estimated duration of 24 months and an estimated budget of 15 million euros that will be financed by SNN, by increasing the share capital of Energonuclear (EN) - the company tasked with the construction, commissioning and operation of Units 3 & 4 - accordingly. The main objectives of this stage are: re-operationalization of project company EN, contracting technical, legal and financial assistance services, contracting engineering services to update the technical procurement specification, launching, selecting and awarding the Engineering, Procurement and Construction Contract in two phases (Phase 1 - Preliminary Works - Limited Notice to Proceed and Phase 2 - Project Implementation - Issuance of the Final Notice to Proceed).
 
Any other studies/reports/evaluations necessary for the configuration of the project within the limits of the budget assigned to this stage shall be contracted within this stage.
 
The second stage consists of the preliminary works (Limited Notice to Proceed - LNTP) - Phase 1 of the Engineering, Procurement and Construction (EPC) Contract, with an estimated duration of 18 - 24 months. The objectives of this stage consist in the development, by the EPC contractor, of the critical engineering part of the project, of the nuclear safety documentation and of the local market surveys in order to identify the necessary equipment and service suppliers, so that the total price of the project is fixed for a considerable part of the necessary works and services.
 
The nuclear safety documentation required for obtaining the Nuclear Safety Authorization will also be developed in this stage, as well as the documentation for the project's notification to the European Commission, based on Article 41 of the EURATOM Treaty.
 
At the end of this stage, the feasibility of the project will be re-assessed based on the new technical and economic indicators and the Final Investment Decision will be taken, which will allow moving to project Stage 3.
 
A set of requirements must be met for the Final Investment Decision to be taken, including obtaining the necessary authorizations from the European Commission for the support measures and structuring and closing the project's financing package.
 
The third stage is represented by the effective construction stage (Issuance of the Final Notice to Proceed - FNTP) - Phase 2 of the EPC Contract, with an estimated duration of 69 - 78 months (completion of Unit 3 - 2030 / completion of Unit 4 - 2031), consisting in the effective start of the construction, assembly and commissioning works.
 
One week ago, SNN general manager Cosmin Ghita said that he expects the construction of the new reactors to start in 2024.
 
"We anticipate Unit 3 to be commissioned around 2030 - 2031, according to the Integrated National Energy and Climate Change Plan, which means a mobilization on site around 2024. Preliminary phases are scheduled until then," said Ghita.
 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 3338 / 4680
 

Ascunde Reclama
BREAKING NEWS
ESENTIAL
Andronic and Partners, alături de OxidOS Automotive într-o nouă rundă de finanțare condusă de gigantul global 42dot din grupul Hyundai
Meet the Professionals | Cum se construiește drumul spre parteneriat într-o firmă de top și ce presupune noul statut → De vorbă cu Rebecca Marina, Filip & Company, despre ”rolul cameleonic” al unui partener și responsabilitatea discretă din spatele fiecărui mandat complex: ”Succesul nu este definit doar de finalizarea formală a tranzacției, ci de calitatea relațiilor pe care le lași în urma ta”
Schoenherr, alături de VIG în investiția IFC într-o societate românească de administrare a fondurilor de pensii private. Markus Piuk (Partener) a coordonat echipa
LegiTeam: Reff & Associates is looking for a Junior Associate | Dispute Resolution
Țuca Zbârcea & Asociații, desemnată ”Firma anului în România” la Chambers Europe Awards 2026 | Schoenherr câștigă în Europa de Sud-Est, Kinstellar în CEE, iar Mannheimer Swartling primește distincția la nivel european. Deloitte Legal, premiată ca ”Outstanding Law Firm”
Practica de Energie a firmei Bohâlțeanu și Asociații marchează unul dintre cei mai intenși ani din evoluția sa, cu mandate complexe în proiecte solare, finanțări transfrontaliere, tranzacții M&A multijurisdicționale și proiecte inovative care pot influența dezvoltarea energiei verzi în România | Ionuț Bohâlțeanu (Managing Partner): ”Planurile pentru următorul an sunt de extindere și diversificare a mandatelor în acest domeniu, urmărind implicarea în proiecte care să scoată în evidență potențialul firmei noastre”
Bucharest Arbitration Days 2026: Probele în arbitrajul internațional: principii și practici în evoluție
Meet the Professionals | Din vorbă în vorbă cu Lidia Zărnescu, recent promovată Counsel la Kinstellar despre un parcurs în Dreptul muncii construit cu răbdare și cu oameni valoroși, întâlniți la momentele potrivite: ”Văd cariera ca pe un maraton, nu ca pe un sprint; dacă se „ard” etape, se pierd lecții și valori esențiale. Cred că adevărata valoare a unui avocat stă în modul în care își folosește expertiza pentru a crea valoare pentru cei din jur”
ZRVP, distinsă cu titlul de “Romania Patent Firm of the Year” la gala Managing IP Awards 2026 | De vorbă cu Alina Tugearu (Partener) despre proprietatea intelectuală ca teren de strategie, prevenție și confruntare juridică în dosare cu miză ridicată: ”Am convingerea că implicarea în unele dintre cele mai sofisticate și relevante dosare din piață a contribuit la recunoașterea de care ne bucurăm azi”
CMS a fost alături de Oresa în vânzarea participației deținute la RBC, cu o echipă condusă de partenerii Horea Popescu și Eva Talmacsi (UK). O echipă coordonată de Ana Radnev (Partner) a asistat și creditorii în finanțarea sindicalizată asociată tranzacției
Codezilla și Țuca Zbârcea & Asociații lansează Benvolio, o platformă AI pentru domeniile juridic și fiscal | Gabriel Zbârcea (Managing Partner - TZA): Platforma este deja utilizată zilnic în cadrul echipei noastre
ZRVP și Wolf Theiss vor găzdui pe 3 iunie 2026 un eveniment VIAC pe tema parcursului profesional în arbitrajul internațional
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...