CMS | Romanian government offers companies up to EUR 500,000 to achieve energy efficiency

29 Iulie 2022   |   CMS Romania

For more information on GEO 112 and the Romanian energy sector, contact your CMS client partner or local CMS experts: Anna Morogai.

 
 
On 18 July 2022, Romania enacted Governmental Emergency Ordinance No. 112/2022 (GEO 112), which establishes, amongst others, a financial support scheme for large, medium and small companies aimed at stimulating investments in energy efficiency in Romania.

GEO 112 is designed to provide financial support for businesses in Romania to achieve energy efficiency (EE) by giving grants to companies for implementing energy-saving measures at their industrial and auxiliary buildings or through technological processes; and producing green energy for their own consumption (“EE Financial Scheme”). As part of this EE Financial Scheme, grants will have a minimum value of EUR 50,000 and a maximum value of EUR 500,000 with the exception of those awarded under the de minimis scheme where the maximum value will be EUR 200,000.


The overall budget allocated to the EE Financial Scheme is EUR 411,764,000 of which:

→    EUR 350 million is non-reimbursable external funds allocated to Romania within the Framework of Large-Scale Infrastructure Operational Programme (LSIOP) and financial resources allocated through the Cohesion Fund; and

→    EUR 61,764,000 is from the Romanian state budget allocated through the Ministry of Investments and European Projects.

Who can apply for EE Financial support?

According to GEO 112, the following entities can apply for funding under the EE Financial Scheme:

→    Large companies with more than 250 employees and a net yearly turnover of more than EUR 43 million;

→    Small and medium enterprises (SMEs) and microenterprises with the observance of EU Commission Regulation No. 651/2014 of 17 June 2014 declaring certain categories of aid compatible with the internal market in application of Articles 107 and 108 of the Treaty.

Additionally, the companies must carry out activities for production of goods or provision of services except for real estate investments, consultancy services, technical-assistance services and activities included in Annex No. 1 of Governmental Decision No. 780/2006 on establishing the greenhouse gas emissions trading scheme.

What does the EE Financial Scheme entail?

GEO 112 provides four large categories of investments that may be funded through the EE Financial Scheme:

1.    investments for reducing energy consumption of buildings (except administrative buildings or buildings not used by the company for production or service activities) through works on the buildings’ covering, roofing, cladding including consolidation works, the buildings’ utility systems, and for the purchase of equipment, machinery and specific facilities needed to produce the energy required for the buildings;

2.    investments in specific equipment, machinery and tools needed for generating energy from renewable sources (except biomass) for the consumption of companies that fall within the specific production capacity of the prosumer (i.e. as defined in Law No 123/2012 on Electricity and Natural Gas);

3.    investments in energy efficiency measures at the level of cogeneration or trigeneration units, existing or new, including investments for modernisation, rehabilitation and the increase of already installed capacities from renewable sources intended for their own consumption, which falls within the specific production capacity of the prosumer;

4.    investments to reduce energy consumption and greenhouse gas emissions through systems dedicated to modernising, monitoring and making energy consumption more efficient, which will necessarily include the installation of an energy management system (EMS) that provides overall metering of energy consumption at the company level, produces statistics on consumption, records and analyses centralised data, reports regularly on these data and makes energy consumption more efficient in real time. The purchase of specific equipment, machinery and tools that are part of the production and service process is possible if it is for the replacement of current equipment, machinery and tools with higher energy consumption and will lead to a reduction of energy consumption compared to the initial consumption.

How does it work?

The grants from the EE Financial Scheme will be awarded following a call for projects, and will observe the principles of transparency and competitiveness. Companies must submit a single application that may cover more than one industrial facility.

The applications must be submitted exclusively through the “IMM Recover” platform. The same platform will be used for evaluating and selecting the successful applicants for the funding of their projects.

Following the call for projects - within the limits of the EE Financial Scheme’s budget - a funding contract will be concluded by the LSIOP Management Authority with the applicant that meets the selection criteria set out in Article 13 and in Annex No. 1 to GEO 112.

To be eligible for funding, the applicant companies must also meet a range of criteria listed in Article 11 of GEO such as:

►    they should have been incorporated prior to 31 Dec 2021;

►    they should not have received financial support from public funds, including European Union funds, in the last five years for the same eligible costs;

►    they must submit an energy consumption analysis, carried out by an independent and authorised expert, containing initial and projected specific energy parameters that represent minimum targets to be met by the beneficiaries at the end of the project-implementation period and to be maintained thereafter;

►    they must ensure the sustainability of the investment project (i.e. maintaining the specific energy parameters to which each company committed) for a period of at least five years after the expiry of the project implementation period; etc.

The beneficiaries of the funding must finish their investment projects and achieve the assumed energy parameters by 31 December 2023. If the beneficiaries do not achieve the specific energy parameters assumed through their funding application, they will be liable to repay the amounts received, plus applicable interest.

For more information on GEO 112 and the Romanian energy sector, contact your CMS client partner or local CMS experts: Anna Morogai.
 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 840 / 4349
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
RTPR a asistat PragmaGO la intrarea pe piața din România prin achiziția Omnicredit. Echipa a fost coordonată de Alina Stăvaru (Partner) și Ianita Țui (Counsel)
Andreea Zvâc face un pas înainte în carieră și devine Partener în cadrul biroului Wolf Theiss din București | Bryan W. Jardine (Managing Partner): Promovarea sa reflectă nu numai contribuțiile profesionale remarcabile la dezvoltarea departamentului său, ci și rolul semnificativ în consolidarea poziției generale a firmei pe piața din România
Bondoc & Asociații a asistat TDI Renewables, unul dintre principalii actori în domeniul dezvoltării regenerabile, într-o restructurare internațională
Cine sunt și cum gândesc profesioniștii evidențiați de Legal 500 în GC Powerlist Romania | De vorbă cu Mihaela Scărlătescu, Head of legal - Farmexim: „Când ești managerul unei echipe de legal, rolul nu se rezumă doar în a asigura îndeplinirea sarcinilor, ci este de fapt mai mult orientat spre partea umană. Cresc echipe, cresc oameni de niște ani buni și nu există satisfacție mai mare ca atunci când vezi transformarea acestora, acolo unde există ‘sămânța dorinței de a evolua ’ ”
VIDEO | Dicționar de arbitraj: Avansul cheltuielilor arbitrale (Powered by ZRVP)
„The Lawyer European Awards 2024”| Patru firme cu activitate în România concurează pentru titlu la secțiunea ”Law Firm of the Year: South Eastern Europe” | Popescu & Asociații și TZA, pe lista scurtă a premianților. ZRVP, pentru a treia oară în ultimii cinci ani, printre finaliștii secțiunii ”European litigation team of the year”
Rising Stars | Tudor Bonifate, primul admis la Facultatea de Drept și mai apoi șef de promoție în 2022, cu media 10, a ales să profeseze ca avocat la Țuca Zbârcea & Asociații: ”Învăț permanent – de la avocații care mă coordonează, de la colegii mei avocați, de la profesorii cu care am șansa de a colabora la facultate, de la studenții mei. Cred că avocatura mă face un profesor mai bun, după cum profesoratul mă face un avocat mai bun”
Încă un spin-off în piața avocaturii | Luminița Popa și Miruna Suciu, fondatoarele Suciu Popa, o iau pe drumuri diferite. Popa Legal se va focusa pe practica de arbitraj, iar Suciu Partners anunță consolidarea echipei
Țuca Zbârcea & Asociații apără interesele statului român în litigiul inițiat de Damen Holding la Curtea de Arbitraj de la Viena | Legea 187 ̸ 2023 referitoare la guvernanța corporativă a întreprinderilor publice a pus pe butuci modelul de cooperare cu investitorul olandez la Damen Shipyards Mangalia SA, o companie în care statul deține 51%, prin Șantierul Naval 2 Mai SA. Pierderea litigiului antrenează plata unor ”despăgubiri semnificative”
Mușat & Asociații intră în arbitrajul ICSID inițiat de bulgarii de la Eurohold și va lupta, de partea statului român, cu Pinsent Masons și DGKV. Reclamanții și-au ales un arbitru din Anglia
LegiTeam | Mitel & Asociații recrutează avocați stagiari
LegiTeam | Mitel & Asociatii caută avocat cu experiență (Litigii și Soluționare a Disputelor)
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...