CMS | Romania introduces new electricity licensing rules, prioritises offshore wind generation

03 Aprilie 2025   |   CMS Romania

For more information on Romania’s new electricity sector regulations, contact your CMS client partner or these CMS experts Varinia Radu, Ramona Dulamea or Raluca Diaconeasa.

 
 
With the 26 March 2025 adoption of a new regulation approved by Order no. 6/2025, Romania's electricity sector enters a new licensing era under the Romanian Energy Regulation Authority (ANRE). The Regulation, which replaces the rules specified under Order 12/2015, applies to ongoing applications.

The following article outlines the main updates to the licensing regime, highlighting both the provisions and structural clarifications introduced by the new regulation.

    ► Selling electricity outside the testing period

A new provision states that after commissioning for the testing period, there is the option to remain connected outside of the testing period and to remain active in the energy market, provided several conditions in terms of balancing and approval from TSO are met.


This provision still requires additional clarification whether the intended scope is to allow the providers, after having successfully ended the testing period, to remain connected until the electricity generation licence is secured.

    ► Right to update technology between application and construction

A new right has been granted for the setting-up authorisation title holders: applicants may update the technological specifications of their projects between submission and construction, promoting the adoption of innovative solutions in a rapidly evolving sector.

    ► Clarification on funding sources regarding setting-up authorisation

Comfort letters from banks will only be accepted if expressly stated as binding. Where funding is private, evidence of the investor’s actual financial capacity is now required.

    ► Extension of the setting-up authorisation

The title holder will have the right to apply for the extension of its validity before the expiry of the validity period, not less than 30 days before the expiry date of the authorisation of the establishment/licence. If the 30-day deadline is not observed, then the application for extension will be treated as a new authorisation request.

    ► Requirement for the applicant personnel

The Regulation explicitly introduces the requirement for at least two licensed electricians to be directly employed or contracted in the case of a generation and storage licence. For the supply and trading licence, a minimum of three internal employees are now required, each with at least three years experience in the energy sector.

Financial resources required for the electricity supply/trading and aggregation licence

The financial resources required for the obtaining the electricity supply licence, electricity trading licence and aggregation licence is now increased from at least EUR 100,000 to EUR 200,000. This requirement is not applicable to the citizens' energy community or renewable energy community, which require the supply or trading licence.

    ► New grounds for withdrawing the licence

Among other reasons for withdrawing licences, ANRE will withdraw a licence in case of failure to pay contributions due to ANRE or prohibition imposed by the Energy Law 123/2012 for supply to end customers.

    ► New clarifications on provisional licenses

The Regulation introduces more provisions regarding the provisional licence, intended to enable continuity during asset transfers or ownership changes. It allows the acquiring party – who does not yet hold a full licence – to continue operations temporarily.

    ► Offshore wind: a priority

The Regulation marks Romania’s official regulatory recognition of offshore wind as a strategic energy priority. Chapter VII establishes a complete framework for the authorisation and licensing of offshore wind power plants, with provisions tailored to maritime-specific realities and aligned with emerging EU policy objectives.

    ♦   Setting-up authorisation for offshore wind: Offshore wind setting-up authorisations are issued exclusively to holders of exploration permits and concession contracts with the Ministry of Energy.
    ♦   Generation licence for offshore wind: Once construction is complete, a separate licence is required for the electricity generation of the offshore wind facility.

This is Romania’s most detailed licensing path to date and positions the country to competitively pursue offshore wind development in the Black Sea.

For more information on Romania’s new electricity sector regulations, contact your CMS client partner or these CMS experts Varinia Radu, Ramona Dulamea or Raluca Diaconeasa.
 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 100 / 4559
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
Summer Internship-ul Mușat & Asociații, mai mult decât un stagiu de vară: program strategic de formare și recrutare, care le oferă studenților experiență practică autentică, mentorat direct de la parteneri și acces la Fellowship, cu șanse reale de a deveni parte din echipa firmei | De vorbă cu Ștefan Diaconescu (Partner) despre experiență completă a cursanților, cu expunere directă la multiple arii de practică și la cultura organizațională a uneia dintre cele mai mari firme de avocatură din România
Reff & Asociații | Deloitte Legal a asistat dezvoltatorul şi investitorul imobiliar Prime Kapital în emisiunea de obligațiuni de 100 mil. €. Partenerii Andrei Burz-Pînzaru și Irina Dimitriu, în prim plan
League Tables of Legal Advisors (H1 2025) | Piața globală a fuziunilor și achizițiilor a atins 2 trilioane USD – cel mai bun semestru pentru mega-deal-uri din 2020, dar cu cel mai mic număr de tranzacții din ultimele două decenii. CMS și Clifford Chance, printre primele în clasamentul global. Schoenherr are un avans impresionant în Europa și a asistat cele mai multe tranzacții în CEE
Filip & Company a asistat ACP Credit în acordarea unei noi runde de finanțare rețelei de clinici veterinare PartnerVet. Echipa, coordonată de Alexandra Manciulea (partener) și Rebecca Marina (counsel)
Clifford Chance își consolidează practica de Litigii prin recrutarea lui Remus Codreanu ca partener în echipa din București
Kinstellar are un nou Office Managing Partner în București | Iustinian Captariu a preluat managementul biroului de la Victor Constantinescu, cel care a condus echipa locală timp de șase ani, cu rezultate remarcabile. Kristóf Ferenczi, Firm Managing Partner: ”Numirea lui Iustinian face parte din programul nostru de planificare a succesiunii, un element esențial pentru a asigura creșterea și succesul continuu al Kinstellar”
Lexology Energy Rankings 2025 | Cine sunt avocații români care s-au remarcat într-o practică devenită, în ultimii ani, un adevărat laborator de inovație juridică: ZRVP, CMS, TZA și NNDKP au o amprentă bine conturată în Oil & Gas. NNDKP strălucește și în Power & Electricity, unde se remarcă și Kinstellar, dar și în Renewables
ANALIZĂ | Gabriel Resources a deschis o procedură de anulare a hotărârii ICSID prin care Tribunalul arbitral a respins cererea de peste 3 mld. USD privind controversatul proiect minier de la Roșia Montană, iar România a răspuns cu un Contramemoriu care demontează acuzațiile și atacă frontal strategia reclamanților. Dacă statul ar pierde, impactul ar fi devastator pentru finanțele publice și ar compromite rezultatele măsurilor pe care guvernul Bolojan încearcă să le implementeze
CMS | Join Our Team: Tax Consultant - Tax Department
Ana-Maria Baciu, avocatul din România cu cele mai multe nominalizări la gala Legal 500 CEE Awards 2025: Intellectual Property Lawyer of the Year, Romania Lawyer of the Year și CEE Partner of the Year. Astfel de validări contribuie nu doar la consolidarea brandului său personal, ci și la repoziționarea avocaturii de business din România ca un partener credibil, capabil să ofere consultanță sofisticată clienților internaționali
LegiTeam: Lawyer - Dispute Resolution and Employment | GNP Guia Naghi and Partners
Bulboacă & Asociatii caută un Avocat Colaborator pentru Echipa de Tranzacții de Elită (Corporate ̸ M&A)
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...