With the 26 March 2025 adoption of a new regulation approved by Order no. 6/2025, Romania's electricity sector enters a new licensing era under the Romanian Energy Regulation Authority (ANRE). The Regulation, which replaces the rules specified under Order 12/2015, applies to ongoing applications.

The following article outlines the main updates to the licensing regime, highlighting both the provisions and structural clarifications introduced by the new regulation.

    ► Selling electricity outside the testing period

A new provision states that after commissioning for the testing period, there is the option to remain connected outside of the testing period and to remain active in the energy market, provided several conditions in terms of balancing and approval from TSO are met.


This provision still requires additional clarification whether the intended scope is to allow the providers, after having successfully ended the testing period, to remain connected until the electricity generation licence is secured.

    ► Right to update technology between application and construction

A new right has been granted for the setting-up authorisation title holders: applicants may update the technological specifications of their projects between submission and construction, promoting the adoption of innovative solutions in a rapidly evolving sector.

    ► Clarification on funding sources regarding setting-up authorisation

Comfort letters from banks will only be accepted if expressly stated as binding. Where funding is private, evidence of the investor’s actual financial capacity is now required.

    ► Extension of the setting-up authorisation

The title holder will have the right to apply for the extension of its validity before the expiry of the validity period, not less than 30 days before the expiry date of the authorisation of the establishment/licence. If the 30-day deadline is not observed, then the application for extension will be treated as a new authorisation request.

    ► Requirement for the applicant personnel

The Regulation explicitly introduces the requirement for at least two licensed electricians to be directly employed or contracted in the case of a generation and storage licence. For the supply and trading licence, a minimum of three internal employees are now required, each with at least three years experience in the energy sector.

Financial resources required for the electricity supply/trading and aggregation licence

The financial resources required for the obtaining the electricity supply licence, electricity trading licence and aggregation licence is now increased from at least EUR 100,000 to EUR 200,000. This requirement is not applicable to the citizens' energy community or renewable energy community, which require the supply or trading licence.

    ► New grounds for withdrawing the licence

Among other reasons for withdrawing licences, ANRE will withdraw a licence in case of failure to pay contributions due to ANRE or prohibition imposed by the Energy Law 123/2012 for supply to end customers.

    ► New clarifications on provisional licenses

The Regulation introduces more provisions regarding the provisional licence, intended to enable continuity during asset transfers or ownership changes. It allows the acquiring party – who does not yet hold a full licence – to continue operations temporarily.

    ► Offshore wind: a priority

The Regulation marks Romania’s official regulatory recognition of offshore wind as a strategic energy priority. Chapter VII establishes a complete framework for the authorisation and licensing of offshore wind power plants, with provisions tailored to maritime-specific realities and aligned with emerging EU policy objectives.

    ♦   Setting-up authorisation for offshore wind: Offshore wind setting-up authorisations are issued exclusively to holders of exploration permits and concession contracts with the Ministry of Energy.
    ♦   Generation licence for offshore wind: Once construction is complete, a separate licence is required for the electricity generation of the offshore wind facility.

This is Romania’s most detailed licensing path to date and positions the country to competitively pursue offshore wind development in the Black Sea.

For more information on Romania’s new electricity sector regulations, contact your CMS client partner or these CMS experts Varinia Radu, Ramona Dulamea or Raluca Diaconeasa.
 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 190 / 4649
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
Schoenherr asistă Treo Asset Management în vânzarea Maxbet România și Malta către Super Technologies. Echipa implicată în proiect a fost coordonată de Mădălina Neagu (Partner)
LegiTeam: CMS CAMERON MCKENNA NABARRO OLSWANG LLP SCP is looking for: Associate | Commercial group (3-4 years definitive ̸ qualified lawyer)
Filip & Company asistă Continental în vânzarea OESL către Regent. Alexandru Bîrsan (managing partner) a coordonat echipa
Cum a fost integrată Harvey, platforma de inteligență artificială concepută pentru domeniul juridic, într-o firmă de avocatură, fără să schimbe esența profesiei | Experiența Filip & Company, detaliată de Alexandru Bîrsan (Co-Managing Partner) și Andreea Piștea (Project Manager): AI-ul devine un avantaj competitiv atunci când scurtează drumul către analiza de substanță și conturarea strategiei, dar rămâne sigur și util doar într-un cadru în care avocatul validează, decide și își asumă rezultatul
Chambers Global 2026 | RTPR rămâne singura firmă de avocați listată pe prima poziție în ambele arii de practică analizate: Corporate ̸ M&A și Banking & Finance. Filip & Company este în prima bandă în Corporate ̸ M&A. Firmele care au cei mai mulți avocați evidențiați sunt RTPR (9), Filip & Company (8), CMS (6) și Clifford Chance Badea (5)
Bulboacă & Asociații finalizeaza o noua tranzactie de referinta in sectorul medical, dupa securizarea avizelor CEISD si ale Consiliului Concurentei. Echipa de proiect, coordonată de Roxana Tiutiu (Partener)
Clifford Chance a asistat BEI, BERD și BCR în acordul de finanțare semnat cu Scatec pentru dezvoltarea și exploatarea unei centrale solare cu o capacitate de 189,7 MWp. Echipă transfrontalieră cu 6 avocați din București în prim plan
Clifford Chance Badea a asistat Electro-Alfa International în IPO-ul de 580 milioane RON, una dintre cele mai de succes listări realizate de o companie antreprenorială din România. Echipa a fost condusă de Radu Ropotă (Partener)
Eversheds Sutherland își întărește linia de arbitraj la București prin cooptarea Luminiței Popa ca partener | Un nume de referință în arbitrajul internațional revine într-o echipă integrată, după perioada dedicată practicii independente
ICC Arbitration Breakfast revine în România cu cea de-a doua ediție - 18 martie, în București
În litigiile fiscale, Artenie, Secrieru & Partners este asociată cu rigoarea și eficiența, grație unei combinații rare de viziune, metodă și capacitate de execuție în dosare grele. De vorbă cu coordonatorii practicii despre noul ritm al inspecțiilor, reîncadrările tot mai frecvente și importanța unei apărări unitare, susținute de specialiști și expertize, într-un context fiscal tot mai imprevizibil
NNDKP obține o decizie semnificativă pentru litigiile privind prețurile de transfer din partea de vest a României. Echipă mixtă, cu avocați din Timișoara și București, în proiect
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...