Suciu Popa | Unlocking the offshore petroleum projects

31 August 2021   |   Cleopatra Leahu, Partner si Noemi Siman, Senior Associate - SUCIU POPA

The legislative process of the Project must be followed with great interest by all operators involved in the development of offshore petroleum projects, in order for the final form of the proposed provisions to correspond with the characteristics and nature of such works.

 
 
After almost 3 years from the enactment of Law no. 256/2018 on certain necessary measures for implementing petroleum operations by titleholders of petroleum agreements related to offshore petroleum blocks (“Offshore Law”), Romania takes another step for unblocking such projects. 

Although the Offshore Law established that the reception procedure would be regulated within 90 days as of the date of entry into force of the aforementioned piece of legislation, according to public available information, the lengthy consultations held between the Ministry of Energy and the Competent Authority for Regulating Petroleum Operations in the Black Sea (“ACROPO”) resulted in extended delays.

A first attempt in order to develop the legislative framework with regard to the reception procedure was initiated on 19 November 2020, when a Draft Government Decision was published on the website of the Ministry of Economy, Energy and Business.

After almost 1 year of passivity, on 27 August 2021, a new form of the reception procedure was published on the Ministry of Energy website, respectively the Draft Government Decision on the approval of the Procedure for the reception of works related to the petroleum operations conducted by the titleholders of petroleum agreements pursuant to Law no. 256/2018 on certain necessary measures for implementing petroleum operations by titleholders of petroleum agreements related to offshore petroleum blocks (the "Project").

In a nutshell, according to the Project, the reception of works represents a component of the quality system and is a complex process, which will certify, in accordance with the law, the completion of works performed under the Offshore Law. The provisions of the Project establish the following main aspects: (i) the organization of the reception procedure; and (ii) the allocation of responsibilities.

The participants within the reception procedure will be:

            (i)                 the titleholders of the authorization deed;


            (ii)               the contractor which performed the execution of the works;

            (iii)             the designer of the works;

            (iv)              the Independent Body/Independent Examination Entity chosen by the titleholder of the authorization deed;

            (v)                the representative (s) of the Ministry of Energy;

            (vi)              other competent institutions or specialists within the oil and natural gas field, as guests of the Ministry of Energy.

The Ministry of Energy shall be entitled to grant the final act of reception of the works executed further to the authorization deed.

The reception procedure shall be performed for all the works envisaged by the authorization deed, in accordance with the documentation based on which it was issued, and shall be admitted or rejected on motivated grounds. In case of rejection, the titleholders of the authorization deed shall have the obligation to remedy the ascertained problems and the reception procedure shall be re-performed with regard to the identified issues.

In order to fulfil the reception procedure, the Ministry of Energy and ACROPO shall each appoint one/two representatives, who shall be a part of the competent committee for: (i) analysing the reports prepared in accordance with the proposed provisions of the Project; and (ii) communicating to the titleholder of the authorization deed the document certifying the reception of works.

Unlike the draft of the reception procedure proposed in 2020, the Project does not contain any provision regarding the possibility of taking over a part of the works, during a certain physical stage of execution.

According to the public available information, the observations or suggestions with regard to the Project shall be submitted until 6 September 2021.

In this context, the legislative process of the Project must be followed with great interest by all operators involved in the development of offshore petroleum projects, in order for the final form of the proposed provisions to correspond with the characteristics and nature of such works.

Suciu Popa is a top law firm with a full-service practice, with notable performances within all areas of business law, including dispute resolution and arbitration, real estate, administrative disputes, project development, energy & renewables, being constantly ranked by all local and international directories in the top tiers of legal services providers. Fully committed to making a difference on the Romanian market, Suciu Popa relies on the solid experience and reputation of its attorneys and partners, built over more than 20 years of acting for multinational clients, strategic investors and investment funds, public authorities and international financial institutions, in some of the most complex cross-border transactions, investment projects and dispute resolution cases.

 
 

PNSA

 
 

ARTICOLE PE ACEEASI TEMA

ARTICOLE DE ACELASI AUTOR


 

Ascunde Reclama
 
 

POSTEAZA UN COMENTARIU


Nume *
Email (nu va fi publicat) *
Comentariu *
Cod de securitate*







* campuri obligatorii


Articol 1738 / 4263
 

Ascunde Reclama
 
BREAKING NEWS
ESENTIAL
Filip & Company a asistat grupul Digi la contractarea unui două împrumuturi în valoare peste 117 mil. € și, respectiv, de 50 mil. €
Senior Lawyer Employment | Reff & Associates
Proiectul parcului fotovoltaic de la Ovidiu face un pas înainte. MPR|Partners a fost alături de EnPower Energy pentru coordonarea procedurii de obținere a acordului de construire, cu o echipă de avocați coordonată de Gelu Maravela (partener fondator) și Dana Rădulescu (partener)
Finanțele au demarat procedura de selecție a firmelor de avocați pentru un proiect ce presupune asistență consistentă în baza dreptului englez. Contract pe 3 ani, tarife orare de cca. 1.900 lei
Cine sunt și cum gândesc profesioniștii evidențiați de Legal 500 în GC Powerlist Romania | De vorbă cu Alexandru Berea, General counsel la BCR: ”Prin colaborare putem genera schimbări semnificative nu doar în interiorul profesiei noastre, ci și în societate in general. Prin natura muncii noastre, nu numai că răspundem la nevoile imediate ale societății, dar suntem și arhitecți ai viitorului acesteia, contribuind la definirea și modelarea unui cadru normativ care să orienteze comportamentul și deciziile individuale și colective pe termen lung”
Rebecca Marina, counsel în cadrul firmei Filip & Company după ultima rundă de promovări: “Am găsit aici oameni care îmi împărtășesc principiile și valorile de viață și care mi-au devenit prieteni și mentori sau pentru care eu am devenit mentor mai târziu. Orice promovare vine cu responsabilități și noi roluri în echipă”
Patru case locale de avocați rămân în topul global al celor mai bune 100 de firme implicate în arbitraje internaționale | Cum sunt prezentate în GAR 100 (2024), ce mandate au avut și ce spun clienții despre avocați și prestațiile acestora. TZA, ZRVP, LDDP și SP asistă clienți în arbitraje cu pretenții de 15,7 miliarde de dolari
Kinstellar a asistat BIG Mega Renewable Energy cu privire la finanțarea de 92 mil. € cu BERD și OTP Bank pentru construcția și operarea Parcului Eolian Urleasca
Răzvan Gheorghiu-Testa, fondator al Țuca Zbârcea & Asociații, inclus în „Top 50 Cei Mai Influenți Oameni de pe Piața Imobiliară din România”
Wolf Theiss a asistat AIRSOL în legătură cu achiziția MedAir Oxygen Solution | Emanuele Lainati, Legal Affair Manager SOL Group: “Expertiza, dedicarea și abordarea proactivă a avocaţilor Wolf Theiss au fost esențiale pentru încheierea cu succes a tranzacției”
Filip & Company a asistat Centrokinetic, în parteneriat cu Agista, în achiziția pachetului majoritar de părți sociale ale clinicii Socrates din Timișoara
Arbitrajul ICSID cerut de Nova Group Investments a ajuns la final | Statul român așteaptă decizia, după ce tribunalul a declarat închisă procedura în litigiul în care pretențiile se ridică la 345 mil. E. Ce onorarii au fost plătite firmelor de avocați care au asigurat apărarea
 
Citeste pe SeeNews Digital Network
  • BizBanker

  • BizLeader

      in curand...
  • SeeNews

    in curand...