
Developing Renewables in Romania: PUZ or Pass?
17 Octombrie 2022
Mihaela Nyerges, Partener - Vlăsceanu, Nyerges & PartnersThe practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate.
![]() |
One of the most frequent questions asked there days by renewables investors and developers is whether PUZ is still required for developing small renewable power projects in Romania (below 50 ha). The relevance of this question is huge as the answer impacts on the duration of the development process with up to 9 months.
To answer, brief preliminary comments should be made regarding the general construction permitting rules, depending on the various types of lands.
1. Types of lands
The following lands qualifications are relevant for the current topic:
(i) from the perspective of their location, the lands can be (a) located intra-muros (within the buildable perimeter of the respective territorial administrative unit) or (b) located extra-muros (outside such perimeter);
(ii) from the perspective of their destination, the lands can be, among others, (a) agricultural lands or (b) yards-constructions lands;
(iii) from the perspective of their fertility class, the agricultural lands are split into 5 fertility classes, ranging from very fertile land (Class I) to very low fertile land (Class V); the fertility class is established based soil analysis made by experts within the county Office of Pedological Studies.
2. General construction rule
As a general rule, all constructions may be erected only on lands (i) located intra-muros and (ii) qualifying as “yards-constructions”.
If the targeted land qualifies as extra-muros and agricultural land (which is typically the case with the land suitable for renewable projects),
(i) the land should be first requalified from extra-muros into intra-muros land by means of a PUZ;
(ii) no additional formalities should be done for converting the land from agricultural land to “yards-construction” land, as such conversion occurs automatically through the issuance of the building permit.
3. Exception dedicated to renewable energy projects
Late July this year, an exception from the above rule was adopted, expressly allowing the construction of renewable power generation projects on extra-murros lands if the following conditions are met:
(i) land has fertility class III, IV and V; and
(ii) land does not exceed 50 ha.
Therefore, projects falling within the above limitations no longer need to obtain requalification of the land from extra-muros to intra-murros land through a PUZ.
4. Need of a PUZ in case of renewable projects below 50 ha
Therefore, do we still need or not a PUZ for developing renewable on land with fertility class III, IV and V which does not exceeds 50 ha?
The practice of the authorities seems to differ: there are local authorities that request a PUZ for the issuance of the building permit, and authorities that no longer impose such an obligation through the urban planning certificate. We have also encountered a case where the authority changed its mind after having issued an urban planning certificate whereby no PUZ was requested.
Nevertheless, it should be mentioned that PUZ has multiple roles, not just the introduction of land into intra-murros area, as explained below:
(i) according to the general construction law (with certain exceptions not applicable hereto), the building permit may be issued only if (a) there is an urban documentation approved regarding the respective land, setting out the legal, technical and economical regime of the land and (b) the envisaged construction is compatible with the rules set out by the respective urban documentation;
(ii) all communes and towns in Romania must have an urban documentation approved – namely a general urban plan (“PUG”) adopted by the local authorities setting out (a) the function of each land (such as residential, industrial etc.) and (b) the applicable urbanism parameters and limitations (such as land occupation percentage, land occupation coefficient, height regime, etc.);
(iii) PUG is a sufficient urbanism documentation for the issuance of a building permit if (a) it provides the legal, technical and economical regime of the targeted land and (b) the envisaged project is compatible with the regime set out thereby;
(iv) if (a) the PUG does not provide the legal, technical and economical regime of the targeted land or (b) the envisaged construction is not compatible with the rules set out by the PUG for the targeted land or (c) there is no PUG in place (for example, it was never approved, it expired, it was cancelled in court or suspended), the developer must obtain a zonal urban plan (“PUZ”) whereby to adopt/amend the urbanism rules so that they are compatible with the project;
(v) generally, PUGs do not regulate extra-muros land or do not establish an urbanism function/regime compatible with renewable projects;
(vi) very recently, a new exception from the need to adopt an urbanism documentation was added in case of other specific types of constructions allowed on extra murros land.
Further to the above, PUZs are still needed for developing renewable projects on lands below 50 ha in order to establish the function and urbanism parameters of the respective land that are compatible with the envisaged project. Nevertheless, a case-by-case assessment should be made regarding the PUG rules applicable on the respective land. Such assessment should be made by the consultants of the developer, without simply relying on the assessment made by the local authorities when issuing the urbanism certificate.
Publicitate pe BizLawyer? |
![]() ![]() |
Articol 942 / 4580 | Următorul articol |
Publicitate pe BizLawyer? |
![]() |

Țuca Zbârcea & Asociații, la finalizarea proiectului în care a asistat Vodafone România la achiziția Telekom România Mobile Communications: O tranzacție de durată, sofisticată, care a necesitat multă dedicare, pricepere și inspirație
Filip & Company asistă DIGI Romania la achiziția unei părți din Telekom România Mobile Communications | Echipa implicată în proiect a fost coordonată de Alexandru Bîrsan (managing partner)
CMS CAMERON MCKENNA NABARRO OLSWANG LLP SCP is looking for junior lawyers
Lexology Competition Rankings 2025 | Cine sunt avocații români care modelează practica de concurență pe piața locală: Cătălin Suliman (Filip & Company) și Georgiana Bădescu (Schoenherr), printre avocații considerați Thought Leaders. Manuela Guia (GNP Guia Naghi & Partners), Georgeta Dinu (NNDKP), Andreea Oprișan și Raluca Vasilache (Țuca Zbârcea & Asociații), în nucleul de forță al practicii pe piața locală
KPMG Legal - Toncescu și Asociații îl recrutează pe Alexandru Slujitoru de la Reff & Asociații, pe poziția de Partener. Ramona Jurubiță, reconfirmată pentru al treilea mandat în funcția de Country Managing Partner al KPMG în România și Moldova
LegiTeam: Zamfirescu Racoţi Vasile & Partners recrutează avocati stagiari promoția septembrie 2025 | Litigii
Decizie ÎCCJ: O victorie fiscală de referință în materia cheltuielilor intra-grup internațional și a reciclării deșeurilor de ambalaje, obținută de avocații Mușat & Asociații | Echipă interdisciplinară, coordonată de partenerii Angela Porumb și Răzvan Graure
Avocații PNSA au stat alături de compania locală Bit Soft în tranzacția prin care grupul canadian Volaris a intrat pe piața românească a tehnologiei pentru ospitalitate. Echipa pluridisciplinară a fost coordonată de partenerul Bogdan C. Stoica
Instanța de judecată a constatat deductibilitatea serviciilor intra-grup de marketing și negociere, respectiv a serviciilor de cercetare și dezvoltare fără posibilitatea organelor fiscale de a evalua oportunitatea acestor servicii | Echipa Băncilă, Diaconu și Asociații, condusă de Emanuel Băncilă, a obținut victoria
Practica de M&A de la Volciuc-Ionescu accelerează într-o piață mai activă, unde conformarea multiplă și mecanismele sofisticate de preț ̸ structurare ridică miza juridică. “O tranzacție este cu adevărat de succes dacă, după closing, integrarea noii afaceri decurge fluent, sinergiile preconizate se realizează efectiv și nu apar probleme majore care să-i erodeze valoarea”, spun avocații | În spatele fiecărui mandat finalizat se află o combinație atent dozată de expertiză, colaborare și reziliență
Radiografia unui an intens în practica de Employment la KPMG Legal – Toncescu și Asociații | Arhitectura normelor de dreptul muncii arată ca un șantier în lucru: reglementări noi, intenții bune, dar și intersecții nerezolvate între acte normative, zone fără busolă și practici care alunecă în interpretări divergente. De vorbă cu membrii echipei despre provocările perioadei, proiectele cheie și prioritățile clienților, în linie cu valul normativ
Dr. Cosmin Vasile (Managing Partner ZRVP) va susține un curs de arbitraj la INPPA: “Noțiuni introductive de arbitraj comercial – un ghid practic pentru începători”, desfășurat în cinci ateliere | Înscrierile se fac până pe 7 octombrie
-
BizBanker
-
BizLeader
- in curand...
-
SeeNews
in curand...